Revised Capital Programme 2024/25
Decision Maker: Health and Housing
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
Decisions:
The Director of Resources and Deputy Chief Executive submitted a report seeking approval for the 2024/25 revised estimate for this Committee’s capital programme.
Six capital schemes for this Committee’s original estimate budget, totalling £3,166,080 were approved by the Policy and Finance Committee and Full Council at their meetings in February 2024 and March 2024 respectively.
At the 2023/24 year end six capital schemes had not been completed. The total unspent budget of £438,160 for these schemes, known as slippage, was moved into the 2024/25 capital programme budget, after approval by this Committee on 6 June 2024.
Furthermore, there have been two transfers between existing schemes with no overall financial impact, and an additional budget for an existing scheme, Disabled Facilities Grants, totalling £85,930.
As a result of the above, the total approved budget for this Committee’s capital programme of eight schemes was £3,690,170.
The proposed revised estimate for this Committee’s 2024/25 capital programme was £1,972,780 which was a £1,717,390 reduction from the previously approved capital budget. It was recommended that budgets totalling £1,717,390 be moved to the 2025/26 financial year.
It was further noted that at the end of December 2024, £579,691 had been spent or committed. This was 29.4% of the revised capital programme for this Committee.
RESOLVED THAT COMMITTEE:
1. Approve the 2024/25 revised estimate of £1,972,780 for this Committee’s capital programme, as set out in Annex 1 of the report.
2. Approve the move of the capital scheme budgets shown at paragraph 3.5 of the report from 2024/25 to 2025/26.
Report author: Averil Crowther
Publication date: 04/02/2025
Date of decision: 16/01/2025
Decided at meeting: 16/01/2025 - Health and Housing