329 Overall Capital monitoring 2022/23 PDF 135 KB
Report of Director of Resources
enclosed.
Minutes:
The Director of Resources submitted a report for information on the progress on the Council’s approved 2022/23 capital programme for the period to the end of July 2022.
At the end of July 2022 £696,433 had been spent or committed. This was 10.9% of the overall capital programme budget for 2022/23.
A summary of progress on the thirty-nine schemes in the capital programme at the end of July 2022 was as follows:
· Three schemes were complete
· Twenty schemes were currently expected to be completed in-year
· There was no certainty that ten of the schemes would be completed in-year
· One scheme was on hold
· Two schemes would not be completed in-year
· Three schemes were on-going Housing related grants schemes.