Issue - meetings

Revised Capital Programme 2022/23

Meeting: 26/01/2023 - Economic Development (Item 663)

663 Revised Capital Programme 2022/23 pdf icon PDF 85 KB

Report of Director of Resources enclosed

Minutes:

The Director of Resources submitted a report seeking Committee’s approval of the revised estimate for this Committee’s capital programme for the current financial year.

 

The revised estimate for this Committee’s 2022/23 capital programme is nil, which is a £54,750 reduction from the previously approved capital budget.

 

It was proposed to members that the budget of £54,750 on one scheme be moved to the 2023/24 financial year.

 

RESOLVED THAT COMMITTEE

 

1.    Approved the 2022/23 revised estimate of nil for this Committee’s capital programme.

 

2.    Approved the move of £54,750 capital budget from 2022/23 to 2023/24 for the Economic Development Initiatives scheme.